Studiu de caz M/V “GULIZAR ANA”


Atasament

After loading of 5th steel coils on 9th September at 20.55 hrs/lt vessel began to lean on starboard side till the vessel's accommodation has propped on main deck of floating crane "Dobrinesti 2"

The list of the vessel has been of 51º ,at this angle the river water was at not more that 20 centimeter of  hatch coaming , engine room and starboard side crew quarter have been flooded.

Immediately after the incident, four steel coils have been discharged and rescue operation started.

On 21st September 2006 rescue operations have been completed and vessel  brought on seaworthiness condition.